The partial commissioning of BA1 of Main DC Offenbach took place successfully on May 21, 2021 thanks to the great team effort of the Data Center Group as general transferee.
Six months after the BA2 was commissioned and 1.5 years after the start of construction.
This means that the end customer (hyperscaler) has 15 MW of IT load available. Another 10 MW will be added by the BA3, which has already been built in parallel in the main areas, so that it can be assumed that it will be completed on schedule before the end of the year.
Many thanks to all planners, project managers, fitters, co-contractors, experts, authorities and joint venture partners who have contributed to this great success.
Main DC Offenbach
A floor area of 7,800 square meters - planned gross floor area of 22,000 square meters - 8,000 square meters for the computer and server landscape, which will be installed in around 3,300 racks.
Are you interested in the complete reference report on the Main DC project? You can find it here.