28.05.2021
The partial commissioning BA1 of the Main DC Offenbach took place thanks to the great team effort of the DC-DataCenter-Group as general transferee
The partial commissioning of BA1 of Main DC Offenbach took place successfully on May 21, 2021 thanks to the great team effort of the DC-DataCenter-Group as general transferee.
Six months after the BA2 was commissioned and 1.5 years after the start of construction.
This means that the end customer (hyperscaler) has 15 MW of IT load available. Another 10 MW will be added by the BA3, which has already been built in parallel in the main areas, so that it can be assumed that it will be completed on schedule before the end of the year.
Many thanks to all planners, project managers, fitters, co-contractors, experts, authorities and joint venture partners who have contributed to this great success.
A floor space of 7,800 square meters - planned gross floor area of 22,000 square meters - 8,000 square meters for the computer and server landscape, which are installed in around 3,300 racks.
Upon request, the DATA CENTER GROUP as your reliable partner, whether as a general transferee or general contractor, will take care of the smooth construction of your data center, from planning to handover, so that you can focus on your core competencies. Contact us now.
DC-Datacenter-Group GmbH
In der Aue 2
57584 Wallmenroth
Germany
You can reach us during our business hours Monday to Friday from 08:00 to 17:00 under the following phone number:
Phone: +49 2741 9321-0
Fax: +49 2741 9321-111
© DC-Datacenter-Group GmbH
Phone +49 2741 9321-0